Other works

M70 Motorway,
Control Analysis of an Extradosed P.C Bridge

Charged by the Contractor Hídépítő Ltd. Pont-TERV Ltd. has made the independent statical control analysis for the superstructure of the H7 bridge at the junction of the M7 and M70 Motorways on the Becsehely-Letenye section

The superstructure is a two-span extradosed P.C. beam bridge, witha a total length of 114.24m. The spans are 61.98+52.56m long. The cross section is a three-cell P.C. box girder.

For the statical modelling of the superstructure the TDV RM2000 program has been used.